on track
NEJAVI-KROGER-2700

NEJAVIPM for Kroger — Accelerated 12-Month Deployment Plan (2,700 Stores)

Turnkey IoT telemetry and energy optimization deployment across 2,700 Kroger supermarkets in 12 months with peak 400 stores/month commissioning. • Sponsor: Kroger Executive Sponsor (Facilities & Cloud IT)

CPI (Cost Efficiency)
0.98Over Budget

Cost Variance (CV): -$13,600

SPI (Schedule Efficiency)
0.19Behind Schedule

Schedule Variance (SV): -$2,983,600

Earned Value (EV)
$706,400

Planned Value (PV): $3,690,000

Estimate at Completion (EAC)
$2,857,143

Total Budget (BAC): $2,800,000

Earned Value (EVM) S-Curve Baseline

Planned Value (PV) vs Earned Value (EV) vs Actual Cost (AC)

EV (Earned)
PV (Planned)
AC (Actual)

Critical Path Analysis

Zero Total Float (Slack = 0d)

5 Tasks

Any delay on these tasks directly slips the project final go-live date.

Top High-Exposure Risks

RSK-K01Score: 20 / 25

Emerson E2 / Danfoss Firmware Version Incompatibility (287 Units)

Kroger Facilities & vendor update program active; rolling pre-wave validation 3 weeks ahead. Unprepared units re-sequenced without stalling wave.

RSK-K02Score: 15 / 25

Zscaler ZPA Connector & IPSec Tunnel Provisioning Bottleneck

Dedicated Kroger Network SME assigned with 2-day SLA; pre-wave automated port/tunnel diagnostic check executed 14 days before wave launch.

RSK-K03Score: 12 / 25

Commissioning Throughput Ceiling (400 Stores/Month Target)

Added +5 NEJAVI and +8 U.S. partner FTE under authorized subcontractor framework.